Major update on works for Liverpool's ‘most contentious’ road after husband and wife's tragic death

The start date for work to upgrade “the most contentious piece of road in Liverpool” has been revealed. Before Liverpool Council broke up for Christmas, leaders signed off on proposals to award a £1.8m contract for upgrades along Queens Drive.

The work is focused at the southern end of the road around Sefton Park, Mossley Hill and Penny Lane. According to officials, this aims to improve journey times and reliability, reduce congestion, enhance safety by reducing collisions and improve access to essential services.

The works were the subject of a backlash from opposition politicians who are asking the local authority to look again at the project over a perceived lack of public consultation. After a call-in was rejected, the local authority has now revealed when work will get underway.

Flooding under the bridge at Queens Driveplaceholder image
Flooding under the bridge at Queens Drive | LDRS

In its justification for carrying out the work, Liverpool Council said improvements would be made to the carriageway, footways and highway drainage infrastructure. This comes following criticism for the local authority on its management of flooding around Queens Drive after the tragic death of Elaine and Philip Marco in August 2023.

A senior coroner told their inquest last year how city officials had failed to recognise a risk to life caused by flooding in the area. Cllr Richard Kemp, who led the call-in of the plans, described the stretch as “the most contentious piece of road in Liverpool.”

In a written answer to a question about the 22-week scheme, city council officials confirmed when work would get going. The reply said: “Works are due to commence on site in March 2026.

“A detailed programme has not been shared with affected communities due to the fact that the report was called in and the programme could not be discussed with the intended contractor due to the call in.” Contractors are to hold a series of public engagement events ahead of work getting underway.

The written response explained more about the nature of the road maintenance. It said: “The wider highway improvement works funded by the Combined Authority are primarily maintenance-focused in nature, such as addressing carriageway condition and upgrading of drainage assets and infrastructure.

“Schemes of this type and nature that have and continue to be delivered by the council take the approach of engagement with affected residents and stakeholders via appropriate communications, including engagement events, letter drops and social media platforms. The measures to be implemented to manage traffic flow and access will include early stakeholder engagement to identify access requirements which will need to be accommodated throughout the duration of the works.”

Given the five month duration of the scheme, officials have set out how they expect large vehicles to operate around the area. The statement added: “Construction vehicle movements will be planned to avoid peak traffic periods wherever possible, with deliveries and removal of waste coordinated to minimise congestion and disruption.”